N84 Grid

Friston 400kV Substation

NESO connection site, host NGET.

Contracted here2.48 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,480 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
East Anglia One North31 May 202430 Oct 2029860 MW
LionLink (EuroLink)14 May 202431 Oct 20321,600 MW
East Anglia One North31 May 202431 Oct 203420 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2029: 860 MW2032: 2.5 GW2034: 2.5 GW2029203020312032203320342.5 GW
0 MW1.3 GW2.5 GW2029: 860 MW2032: 2.5 GW2034: 2.5 GW20292031203320342.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029860 MW
20322,460 MW
20342,480 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1East Anglia One North860 MW0 MW30 Oct 2029not statedgate not printedAwaiting Consents
2LionLink (EuroLink)1,600 MW860 MW31 Oct 2032not statedgate not printedScoping
3East Anglia One North20 MW2,460 MW31 Oct 2034not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO Interconnector Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291860 MW
203211,600 MW
2034120 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
LionLink (EuroLink)Interconnector1,600 MW31 Oct 2032Scoping
East Anglia One NorthOffshore wind880 MW31 Oct 2034Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.