LionLink (EuroLink)

Developer as published, connection site, reference: National Grid Interconnector Holdings Limited. Friston 400kV Substation (NGET). PRO-000983.

Sign in to watch this project
Capacity1,600 MWInterconnector
Connection date31 Oct 2032Status as printed: Scoping
First date seen 30 Oct 2024, difference +2923 dayscalculated by N84
MW ahead in N84's order at this site860 MWcalculated by N84

Connection date, edition by edition

20242026202820302032File dated 2025-07-22: connection date 2024-10-30Oct 2024File dated 2026-10-20: connection date 2032-10-31Oct 203222 Jul202520 Oct2026
20242026202820302032File dated 2025-07-22: connection date 2024-10-30Oct 2024File dated 2026-10-20: connection date 2032-10-31Oct 203222 Jul202520 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2032 (previous file: 30 Oct 2024), 2,923 days later. N84 holds no copy between 22 Jul 2025 and 20 Oct 2026; this change happened at some point in that time. +2923 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO Interconnector Register, file dated 20 Oct 2026, row 21Receipt: NESO Interconnector Register, file dated 22 Jul 2025, row 19

Supported by National Energy SO Open Data