N84 Grid

Hawthorn Pit 400kV Substation

NESO connection site, host NGET.

Contracted here3.98 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,981 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Morven A Offshore Wind Farm (Prev Phoenix 1A)31 May 202431 Oct 20311,500 MW
Icewind Hawthorn Pit31 May 202431 Oct 20311,000 MW
Hawthorn Pit Green Energy Centre31 May 202431 Oct 20321,025 MW
Isenau Eight31 May 202431 Oct 2033249 MW
ER HTP Energy31 May 202430 Jun 203457 MW
Hazel Solar22 Jul 202531 Oct 2035150 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2031: 2.5 GW2032: 3.5 GW2033: 3.8 GW2034: 3.8 GW2035: 4.0 GW203120322033203420354.0 GW
0 MW2.0 GW4.0 GW2031: 2.5 GW2032: 3.5 GW2033: 3.8 GW2034: 3.8 GW2035: 4.0 GW2031203320354.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20312,500 MW
20323,525 MW
20333,774 MW
20343,831 MW
20353,981 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Morven A Offshore Wind Farm (Prev Phoenix 1A)1,500 MW0 MW31 Oct 2031not statedgate not printedScoping
2Icewind Hawthorn Pit1,000 MW1,500 MW31 Oct 20311gate 1Scoping
3Hawthorn Pit Green Energy Centre1,025 MW2,500 MW31 Oct 2032not statedgate not printedAwaiting Consents
4Isenau Eight249 MW3,525 MW31 Oct 2033not statedgate not printedScoping
5ER HTP Energy57 MW3,774 MW30 Jun 2034not statedgate not printedScoping
6Hazel Solar150 MW3,831 MW31 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203122,500 MW
203211,025 MW
20331249 MW
2034157 MW
20351150 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Morven A Offshore Wind Farm (Prev Phoenix 1A)Offshore wind1,500 MW31 Oct 2031Scoping
Hawthorn Pit Green Energy CentreHybrid1,025 MW31 Oct 2032Awaiting Consents
Icewind Hawthorn PitOffshore wind1,000 MW31 Oct 2031Scoping
Isenau EightBattery storage249 MW31 Oct 2033Scoping
Hazel SolarHybrid150 MW31 Oct 2035Scoping
ER HTP EnergyHybrid57 MW30 Jun 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.