N84 Grid

ER HTP Energy

Developer as published, connection site, reference: ER PROJECT DEVELOPMENT CO LIMITED. Hawthorn Pit 400kV Substation (NGET). PRO-003722.

Sign in to watch this project
Capacity57 MWHybrid
Connection date30 Jun 2034Status as printed: Scoping
MW ahead in N84's order at this site3,774 MWcalculated by N84

Connection date, edition by edition

20342035File dated 2024-05-31: connection date 2034-06-30Jun 2034File dated 2026-10-20: connection date 2034-06-3031 May202420 Oct2026
20342035File dated 2024-05-31: connection date 2034-06-30Jun 2034File dated 2026-10-20: connection date 2034-06-3031 May202420 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 31 May 2024 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.