N84 Grid

Kaimes GSP

NESO connection site, host SPT.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Apr 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue94.8 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Kaimes Energy Park31 May 202430 Apr 202751 MW
Wull Muir Wind Farm7 Nov 20251 Oct 202943.8 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2027: 51 MW2029: 95 MW20272028202995 MW
0 MW50 MW100 MW2027: 51 MW2029: 95 MW20272028202995 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202751 MW
202994.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Kaimes Energy Park51 MW0 MW30 Apr 20271gate 1Scoping
2Wull Muir Wind Farm43.8 MW51 MW1 Oct 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2027151 MW
2029143.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Kaimes Energy ParkBattery storage51 MW30 Apr 2027Scoping
Wull Muir Wind FarmOnshore wind43.8 MW1 Oct 2029Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.