N84 Grid

Killin GSP

NESO connection site, host SHET.

Contracted here0.11 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Nov 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue111 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Ardtrostan Hydro7 Nov 2025 to 30 Nov 2024, date already passed (gate not printed)
  • Killin Farm BESS7 Nov 2025 to 31 Oct 2028 (gate 1)
  • Boreland BESS20 Dec 2024 to 31 Oct 2031 (gate not printed)
  • Finlarig31 May 2024 to 30 Nov 2031 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Ardtrostan Hydro7 Nov 202530 Nov 20240.1 MW
Killin Farm BESS7 Nov 202531 Oct 202849.4 MW
Boreland BESS20 Dec 202431 Oct 203143 MW
Finlarig31 May 202430 Nov 203118.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2024: 0 MW2028: 50 MW2031: 111 MW20242025202620272028202920302031111 MW
0 MW100 MW200 MW2024: 0 MW2028: 50 MW2031: 111 MW2024202620282031111 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20240.1 MW
202849.5 MW
2031111 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Ardtrostan Hydro0.1 MW0 MW30 Nov 2024not statedgate not printedAwaiting Consents
2Killin Farm BESS49.4 MW0.1 MW31 Oct 20281gate 1Scoping
3Boreland BESS43 MW49.5 MW31 Oct 2031not statedgate not printedScoping
4Finlarig18.5 MW92.5 MW30 Nov 2031not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202410.1 MW
2028149.4 MW
2031261.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Killin Farm BESSBattery storage49.4 MW31 Oct 2028Scoping
Boreland BESSBattery storage43 MW31 Oct 2031Scoping
FinlarigHydro and pumped storage35 MW30 Nov 2031Scoping
Acharn Biomass Generating StationBiomass and waste5.6 MWnot statedBuilt
Lubreoch Hydro (Part of Killin Cascade Hydro Scheme)Hydro and pumped storage4 MWnot statedBuilt
Ardtalnaig Hydro Generating StationHydro and pumped storage1.5 MWnot statedBuilt
Ardtrostan HydroHydro and pumped storage0.1 MW30 Nov 2024Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.