The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Ardtrostan Hydro
7 Nov 2025 to 30 Nov 2024, date already passed (gate not printed) - Killin Farm BESS
7 Nov 2025 to 31 Oct 2028 (gate 1) - Boreland BESS
20 Dec 2024 to 31 Oct 2031 (gate not printed) - Finlarig
31 May 2024 to 30 Nov 2031 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Ardtrostan Hydro | 7 Nov 2025 | 30 Nov 2024 | 0.1 MW |
| Killin Farm BESS | 7 Nov 2025 | 31 Oct 2028 | 49.4 MW |
| Boreland BESS | 20 Dec 2024 | 31 Oct 2031 | 43 MW |
| Finlarig | 31 May 2024 | 30 Nov 2031 | 18.5 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2024 | 0.1 MW |
| 2028 | 49.5 MW |
| 2031 | 111 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Ardtrostan Hydro | 0.1 MW | 0 MW | 30 Nov 2024 | not stated | gate not printed | Awaiting Consents |
| 2 | Killin Farm BESS | 49.4 MW | 0.1 MW | 31 Oct 2028 | 1 | gate 1 | Scoping |
| 3 | Boreland BESS | 43 MW | 49.5 MW | 31 Oct 2031 | not stated | gate not printed | Scoping |
| 4 | Finlarig | 18.5 MW | 92.5 MW | 30 Nov 2031 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2024 | 1 | 0.1 MW |
| 2028 | 1 | 49.4 MW |
| 2031 | 2 | 61.5 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Killin Farm BESS | Battery storage | 49.4 MW | 31 Oct 2028 | Scoping |
| Boreland BESS | Battery storage | 43 MW | 31 Oct 2031 | Scoping |
| Finlarig | Hydro and pumped storage | 35 MW | 30 Nov 2031 | Scoping |
| Acharn Biomass Generating Station | Biomass and waste | 5.6 MW | not stated | Built |
| Lubreoch Hydro (Part of Killin Cascade Hydro Scheme) | Hydro and pumped storage | 4 MW | not stated | Built |
| Ardtalnaig Hydro Generating Station | Hydro and pumped storage | 1.5 MW | not stated | Built |
| Ardtrostan Hydro | Hydro and pumped storage | 0.1 MW | 30 Nov 2024 | Awaiting Consents |
Supported by National Energy SO Open Data