N84 Grid

Mablethorpe 400kV Substation

NESO connection site, host NGET.

Contracted here2.47 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date30 Nov 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,474 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
SENECA15 Feb 202230 Nov 20311,200 MW
Mablethorpe Green Energy Centre31 May 202430 Oct 20331,025 MW
EcoMablethorpe31 May 202430 Aug 2034249 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2031: 1.2 GW2033: 2.2 GW2034: 2.5 GW20312032203320342.5 GW
0 MW1.3 GW2.5 GW2031: 1.2 GW2033: 2.2 GW2034: 2.5 GW20312032203320342.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20311,200 MW
20332,225 MW
20342,474 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1SENECA1,200 MW0 MW30 Nov 20311gate 1Scoping
2Mablethorpe Green Energy Centre1,025 MW1,200 MW30 Oct 20331gate 1Awaiting Consents
3EcoMablethorpe249 MW2,225 MW30 Aug 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203111,200 MW
203311,025 MW
20341249 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
SENECAInterconnector1,200 MW30 Nov 2031Scoping
Mablethorpe Green Energy CentreHybrid1,025 MW30 Oct 2033Awaiting Consents
EcoMablethorpeHybrid249 MW30 Aug 2034Scoping
AminthInterconnector0 MW30 Nov 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.