The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- SENECA
15 Feb 2022 to 30 Nov 2031 (gate 1) - Mablethorpe Green Energy Centre
31 May 2024 to 30 Oct 2033 (gate 1) - EcoMablethorpe
31 May 2024 to 30 Aug 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| SENECA | 15 Feb 2022 | 30 Nov 2031 | 1,200 MW |
| Mablethorpe Green Energy Centre | 31 May 2024 | 30 Oct 2033 | 1,025 MW |
| EcoMablethorpe | 31 May 2024 | 30 Aug 2034 | 249 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2031 | 1,200 MW |
| 2033 | 2,225 MW |
| 2034 | 2,474 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | SENECA | 1,200 MW | 0 MW | 30 Nov 2031 | 1 | gate 1 | Scoping |
| 2 | Mablethorpe Green Energy Centre | 1,025 MW | 1,200 MW | 30 Oct 2033 | 1 | gate 1 | Awaiting Consents |
| 3 | EcoMablethorpe | 249 MW | 2,225 MW | 30 Aug 2034 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2031 | 1 | 1,200 MW |
| 2033 | 1 | 1,025 MW |
| 2034 | 1 | 249 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| SENECA | Interconnector | 1,200 MW | 30 Nov 2031 | Scoping |
| Mablethorpe Green Energy Centre | Hybrid | 1,025 MW | 30 Oct 2033 | Awaiting Consents |
| EcoMablethorpe | Hybrid | 249 MW | 30 Aug 2034 | Scoping |
| Aminth | Interconnector | 0 MW | 30 Nov 2031 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.