N84 Grid

Monk Fryston 275kV Substation

NESO connection site, host NGET.

Contracted here2.67 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 Oct 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue2,469.9 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Monk Fryston SSE31 May 202431 Oct 2025320 MW
Monk Fryston BESS31 May 202431 Oct 2029200 MW
Monk Fryston31 May 202431 Dec 2029500 MW
Monk Fryston31 May 202431 Oct 2031400 MW
Monk Fryston Energy Park31 May 202424 Oct 2035800 MW
Monk Fryston27 Sep 202430 Oct 2035249.9 MW
Kingfisher Farm31 May 20242 Jun 2036200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2025: 320 MW2029: 1.0 GW2031: 1.4 GW2035: 2.5 GW2036: 2.7 GW2025202720292031203320362.7 GW
0 MW2.0 GW4.0 GW2025: 320 MW2029: 1.0 GW2031: 1.4 GW2035: 2.5 GW2036: 2.7 GW202520282031203420362.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2025320 MW
20291,020 MW
20311,420 MW
20352,469.9 MW
20362,669.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Monk Fryston SSE320 MW0 MW31 Oct 2025not statedgate not printedConsents Approved
2Monk Fryston BESS200 MW320 MW31 Oct 2029not statedgate not printedScoping
3Monk Fryston500 MW520 MW31 Dec 2029not statedgate not printedScoping
4Monk Fryston400 MW1,020 MW31 Oct 20311gate 1Scoping
5Monk Fryston Energy Park800 MW1,420 MW24 Oct 2035not statedgate not printedScoping
6Monk Fryston249.9 MW2,220 MW30 Oct 20351gate 1Scoping
7Kingfisher Farm200 MW2,469.9 MW2 Jun 20361gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20251320 MW
20292700 MW
20311400 MW
203521,049.9 MW
20361200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Monk Fryston Energy ParkHybrid800 MW24 Oct 2035Scoping
Monk Fryston (Light Valley Solar Limited)Hybrid500 MW31 Dec 2029Scoping
Monk Fryston (ENSO GREEN HOLDINGS X LIMITED)Hybrid400 MW31 Oct 2031Scoping
Monk Fryston SSEBattery storage320 MW31 Oct 2025Consents Approved
Monk Fryston (Downing Renewable Developments LLP)Battery storage249.9 MW30 Oct 2035Scoping
Kingfisher FarmBattery storage200 MW2 Jun 2036Scoping
Monk Fryston BESSBattery storage200 MW31 Oct 2029Scoping
Monk Fryston Tertiary ConnectionBattery storage57 MWnot statedBuilt
Red Hill Energy ParkHybrid0 MW24 Oct 2035Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.