N84 Grid

Strichen GSP

NESO connection site, host SHET.

Contracted here0.22 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date30 Nov 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue126.92 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Bilbo Farm31 May 202430 Jun 202425 MW
Clayfords Energy Storage7 Nov 202530 Jun 202649.9 MW
Bilbo Farm31 May 202431 Oct 203342.1 MW
Hillhead of Gask7 Nov 202530 Nov 20239.5 MW
Coulterfanny PV7 Nov 202531 Oct 20250.17 MW
Strichen GSP7 Nov 202531 Oct 20250.25 MW
Mid Whitestones Farm PV7 Nov 202531 Oct 20279.9 MW
Strichen North BESS31 May 202431 Oct 203325 MW
Cairnstone Estate Solar Wind and Storage7 Nov 202531 Oct 203360 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2023: 10 MW2024: 35 MW2025: 35 MW2026: 85 MW2027: 95 MW2033: 222 MW202320252027202920312033222 MW
0 MW125 MW250 MW2023: 10 MW2024: 35 MW2025: 35 MW2026: 85 MW2027: 95 MW2033: 222 MW2023202620292033222 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20239.5 MW
202434.5 MW
202534.92 MW
202684.82 MW
202794.72 MW
2033221.82 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Bilbo Farm25 MW0 MW30 Jun 20242gate 2Under Construction/Commissioning
2Clayfords Energy Storage49.9 MW25 MW30 Jun 20262gate 2Consents Approved
3Bilbo Farm42.1 MW74.9 MW31 Oct 20332gate 2Scoping
4Hillhead of Gask9.5 MW117 MW30 Nov 2023not statedgate not printedConsents Approved
5Coulterfanny PV0.17 MW126.5 MW31 Oct 2025not statedgate not printedScoping
6Strichen GSP0.25 MW126.67 MW31 Oct 2025not statedgate not printedScoping
7Mid Whitestones Farm PV9.9 MW126.92 MW31 Oct 2027not statedgate not printedScoping
8Strichen North BESS25 MW136.82 MW31 Oct 2033not statedgate not printedScoping
9Cairnstone Estate Solar Wind and Storage60 MW161.82 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202319.5 MW
2024125 MW
202520.42 MW
2026149.9 MW
202719.9 MW
20333127.1 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bilbo FarmHybrid67.1 MW31 Oct 2033Scoping
Cairnstone Estate Solar Wind and StorageHybrid60 MW31 Oct 2033Scoping
Clayfords Energy StorageBattery storage49.9 MW30 Jun 2026Consents Approved
Strichen North BESSBattery storage25 MW31 Oct 2033Scoping
Mid Whitestones Farm PVSolar9.9 MW31 Oct 2027Scoping
Hillhead of GaskOnshore wind9.5 MW30 Nov 2023Consents Approved
Castle of AuchryOnshore wind2.4 MWnot statedBuilt
Mid Backhill Wind FarmOnshore wind2.35 MWnot statedBuilt
RedbogOnshore wind1.6 MWnot statedBuilt
Strichen GSP (Scottish Hydro Electric Power Distribution Plc)Battery storage0.25 MW31 Oct 2025Scoping
Coulterfanny PVSolar0.17 MW31 Oct 2025Scoping