The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Warley
31 May 2024 to 30 Oct 2028 (gate 2) - Warley Battery Energy Storage
31 May 2024 to 31 Oct 2029 (gate 1) - Lebanon Farm 2 BESS
31 May 2024 to 31 Oct 2030 (gate not printed) - Warley PV & BESS
31 May 2024 to 31 Oct 2031 (gate not printed) - St. Marys Lane - Upminster BESS
31 May 2024 to 31 Oct 2036 (gate 1) - Upminster Warley 3
22 Jul 2025 to 31 Oct 2036 (gate 1) - Codham Hall BESS
31 May 2024 to 31 Oct 2037 (gate 1) - Blanket’s Farm
27 Sep 2024 to 31 Oct 2038 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Warley | 31 May 2024 | 30 Oct 2028 | 57 MW |
| Warley Battery Energy Storage | 31 May 2024 | 31 Oct 2029 | 200 MW |
| Lebanon Farm 2 BESS | 31 May 2024 | 31 Oct 2030 | 275 MW |
| Warley PV & BESS | 31 May 2024 | 31 Oct 2031 | 249.9 MW |
| St. Marys Lane - Upminster BESS | 31 May 2024 | 31 Oct 2036 | 240 MW |
| Upminster Warley 3 | 22 Jul 2025 | 31 Oct 2036 | 240 MW |
| Codham Hall BESS | 31 May 2024 | 31 Oct 2037 | 249 MW |
| Blanket’s Farm | 27 Sep 2024 | 31 Oct 2038 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2028 | 57 MW |
| 2029 | 257 MW |
| 2030 | 532 MW |
| 2031 | 781.9 MW |
| 2036 | 1,261.9 MW |
| 2037 | 1,510.9 MW |
| 2038 | 1,710.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Warley | 57 MW | 0 MW | 30 Oct 2028 | 2 | gate 2 | Consents Approved |
| 2 | Warley Battery Energy Storage | 200 MW | 57 MW | 31 Oct 2029 | 1 | gate 1 | Scoping |
| 3 | Lebanon Farm 2 BESS | 275 MW | 257 MW | 31 Oct 2030 | not stated | gate not printed | Scoping |
| 4 | Warley PV & BESS | 249.9 MW | 532 MW | 31 Oct 2031 | not stated | gate not printed | Scoping |
| 5 | St. Marys Lane - Upminster BESS | 240 MW | 781.9 MW | 31 Oct 2036 | 1 | gate 1 | Scoping |
| 6 | Upminster Warley 3 | 240 MW | 1,021.9 MW | 31 Oct 2036 | 1 | gate 1 | Scoping |
| 7 | Codham Hall BESS | 249 MW | 1,261.9 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
| 8 | Blanket’s Farm | 200 MW | 1,510.9 MW | 31 Oct 2038 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2028 | 1 | 57 MW |
| 2029 | 1 | 200 MW |
| 2030 | 1 | 275 MW |
| 2031 | 1 | 249.9 MW |
| 2036 | 2 | 480 MW |
| 2037 | 1 | 249 MW |
| 2038 | 1 | 200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Lebanon Farm 2 BESS | Battery storage | 275 MW | 31 Oct 2030 | Scoping |
| Warley PV & BESS | Battery storage | 249.9 MW | 31 Oct 2031 | Scoping |
| Codham Hall BESS | Battery storage | 249 MW | 31 Oct 2037 | Scoping |
| Upminster Warley 3 | Battery storage | 240 MW | 31 Oct 2036 | Scoping |
| St. Marys Lane - Upminster BESS | Battery storage | 240 MW | 31 Oct 2036 | Scoping |
| Warley Battery Energy Storage | Battery storage | 200 MW | 31 Oct 2029 | Scoping |
| Blanket’s Farm | Battery storage | 200 MW | 31 Oct 2038 | Scoping |
| Warley (tertiary) | Hybrid | 57 MW | not stated | Built |
| Warley (WARLEY BATTERY STORAGE LIMITED) | Battery storage | 57 MW | 30 Oct 2028 | Consents Approved |
| Care Brentwood BEGA | Battery storage | 49.9 MW | not stated | Built |
| Clay Tye Farm Phase 1 | Battery storage | 49.5 MW | not stated | Built |
| Clay Tye Farm Phase 2 | Battery storage | 49.5 MW | not stated | Built |
| Warley 2 (CSE26 LIMITED) | Battery storage | 0 MW | not stated | Scoping |