West Anglia Connection Node G 400kV Substation

NESO connection site, host NGET.

Contracted here1.92 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,920 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Ryhall PV & BESS31 May 202431 Oct 2034400 MW
Spalding High Impact Energy Hub21 Mar 202531 Oct 20341,000 MW
Astwood Solar Farm GEC22 Jul 202531 Oct 2037520 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2034: 1.4 GW2037: 1.9 GW20342035203620371.9 GW
0 MW1.0 GW2.0 GW2034: 1.4 GW2037: 1.9 GW20342035203620371.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20341,400 MW
20371,920 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Ryhall PV & BESS400 MW0 MW31 Oct 20341gate 1Scoping
2Spalding High Impact Energy Hub1,000 MW400 MW31 Oct 20341gate 1Scoping
3Astwood Solar Farm GEC520 MW1,400 MW31 Oct 20371gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203421,400 MW
20371520 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Spalding High Impact Energy HubHybrid1,000 MW31 Oct 2034Scoping
Astwood Solar Farm GECHybrid520 MW31 Oct 2037Scoping
Ryhall PV & BESSHybrid400 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data