N84 Grid

ALNESS GRID

DNO substation.

Contracted here0.20 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Jul 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue199.46 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
ALNESS GRID (bess)20 Sep 202331 Jul 202550 MW
ALNESS GRID (bess)4 Apr 202231 Oct 203056.14 MW
ALNESS GRID (solar)26 Nov 202531 Dec 203015 MW
ALNESS GRID (bess)20 Nov 202431 Jan 203235.12 MW
ALNESS GRID (wind on)7 Jun 202431 Oct 203243.2 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2025: 50 MW2030: 121 MW2032: 199 MW20252026202720282029203020312032199 MW
0 MW100 MW200 MW2025: 50 MW2030: 121 MW2032: 199 MW2025202720292032199 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202550 MW
2030121.14 MW
2032199.46 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1ALNESS GRID (bess)50 MW0 MW31 Jul 2025not statedgate not printedAccepted to Connect
2ALNESS GRID (bess)56.14 MW50 MW31 Oct 2030not statedgate not printedAccepted to Connect
3ALNESS GRID (solar)15 MW106.14 MW31 Dec 2030not statedgate not printedAccepted to Connect
4ALNESS GRID (bess)35.12 MW121.14 MW31 Jan 2032not statedgate not printedAccepted to Connect
5ALNESS GRID (wind on)43.2 MW156.26 MW31 Oct 2032not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025150 MW
2030271.14 MW
2032278.32 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
ALNESS GRID (battery, 56.14 MW)Battery storage50 MW31 Oct 2030Accepted to Connect
ALNESS GRID (battery, 50 MW)Battery storage49.9 MW31 Jul 2025Accepted to Connect
ALNESS GRID (onshore wind, 43.2 MW)Onshore wind43.2 MW31 Oct 2032Accepted to Connect
ALNESS GRID (onshore wind, 36.8 MW)Onshore wind36.8 MWnot statedConnected
ALNESS GRID (onshore wind, 30 MW)Onshore wind30 MWnot statedConnected
ALNESS GRID (onshore wind, 30 MW)Onshore wind30 MWnot statedConnected
ALNESS GRID (battery, 35.12 MW)Battery storage29.9 MW31 Jan 2032Accepted to Connect
ALNESS GRID (solar, 15 MW)Solar15 MW31 Dec 2030Accepted to Connect
ALNESS GRID (onshore wind, 8.55 MW)Onshore wind8.55 MWnot statedConnected
ALNESS GRID (onshore wind, 7.6 MW)Onshore wind7.6 MWnot statedConnected
ALNESS GRID (onshore wind, 4.37 MW)Onshore wind4.37 MWnot statedConnected
ALNESS GRID (hydro, 3.8 MW)Hydro and pumped storage3.8 MWnot statedConnected
ALNESS GRID (onshore wind, 38.4 MW)Onshore wind0 MW30 Jun 2025Accepted to Connect
ALNESS GRID (onshore wind, 9 MW)Onshore wind0 MWnot statedAccepted to Connect
ALNESS GRID (hydro, 9.9 MW)Hydro and pumped storage0 MW31 Oct 2032Accepted to Connect
ALNESS GRID (hydro, 4.1 MW)Hydro and pumped storage0 MW5 Nov 2027Accepted to Connect
ALNESS GRID (onshore wind, 24.8 MW)Onshore wind0 MWnot statedAccepted to Connect
ALNESS GRID (battery, 50 MW)Battery storage0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.