N84 Grid

BURGHFIELD RESERVE

DNO substation.

Contracted here0.16 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date3 Apr 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue155.75 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
BURGHFIELD RESERVE (solar)3 Apr 20253 Apr 202620 MW
BURGHFIELD RESERVE (solar)9 Dec 202031 Dec 202612 MW
BURGHFIELD RESERVE (solar)27 Feb 202627 Feb 202720.95 MW
BURGHFIELD RESERVE (solar)27 Feb 202627 Feb 202755.3 MW
BURGHFIELD RESERVE (other)30 Oct 202331 Oct 203747.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 32 MW2027: 108 MW2037: 156 MW202620282030203220342037156 MW
0 MW100 MW200 MW2026: 32 MW2027: 108 MW2037: 156 MW20262029203220352037156 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202632 MW
2027108.25 MW
2037155.75 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1BURGHFIELD RESERVE (solar)20 MW0 MW3 Apr 2026not statedgate not printedAccepted to Connect
2BURGHFIELD RESERVE (solar)12 MW20 MW31 Dec 2026not statedgate not printedAccepted to Connect
3BURGHFIELD RESERVE (solar)20.95 MW32 MW27 Feb 2027not statedgate not printedAccepted to Connect
4BURGHFIELD RESERVE (solar)55.3 MW52.95 MW27 Feb 2027not statedgate not printedAccepted to Connect
5BURGHFIELD RESERVE (other)47.5 MW108.25 MW31 Oct 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026232 MW
2027276.25 MW
2037147.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BURGHFIELD RESERVE (other, 47.5 MW)Other49.9 MW31 Oct 2037Accepted to Connect
BURGHFIELD RESERVE (solar, 20 MW)Solar20 MW3 Apr 2026Accepted to Connect
BURGHFIELD RESERVE (solar, 12 MW)Solar12 MW31 Dec 2026Accepted to Connect
BURGHFIELD RESERVE (solar, 55.3 MW)Solar0.26 MW27 Feb 2027Accepted to Connect
BURGHFIELD RESERVE (solar, 20.95 MW)Solar0.26 MW27 Feb 2027Accepted to Connect
BURGHFIELD RESERVE (hybrid, 0.22 MW)Hybrid0 MWnot statedAccepted to Connect
BURGHFIELD RESERVE (solar, 49.9 MW)Solar0 MW30 Apr 2026Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.