The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- CARRADALE GRID (hydro)
27 Nov 2024 to 31 Jan 2026, date already passed (gate not printed) - CARRADALE GRID (bess)
8 Apr 2025 to 8 Apr 2026, date already passed (gate not printed) - CARRADALE GRID (wind on)
11 Jan 2023 to 30 Apr 2026, date already passed (gate not printed) - CARRADALE GRID (solar)
22 Feb 2026 to 22 May 2027 (gate not printed) - CARRADALE GRID (wind on)
27 Jan 2020 to 31 May 2028 (gate not printed) - CARRADALE GRID (wind on)
14 Jul 2026 to 29 Sep 2028 (gate not printed) - CARRADALE GRID (wind on)
4 Jan 2024 to 30 Apr 2030 (gate not printed) - CARRADALE GRID (bess)
3 Apr 2024 to 31 Oct 2032 (gate not printed) - CARRADALE (wind on)
24 Oct 2023 to 31 Oct 2034 (gate not printed) - CARRADALE GRID (wind on)
25 Feb 2025 to 31 Oct 2034 (gate not printed) - CARRADALE GRID (solar)
30 May 2025 to 31 Oct 2034 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| CARRADALE GRID (hydro) | 27 Nov 2024 | 31 Jan 2026 | 0.16 MW |
| CARRADALE GRID (bess) | 8 Apr 2025 | 8 Apr 2026 | 49.9 MW |
| CARRADALE GRID (wind on) | 11 Jan 2023 | 30 Apr 2026 | 52.8 MW |
| CARRADALE GRID (solar) | 22 Feb 2026 | 22 May 2027 | 14.2 MW |
| CARRADALE GRID (wind on) | 27 Jan 2020 | 31 May 2028 | 50 MW |
| CARRADALE GRID (wind on) | 14 Jul 2026 | 29 Sep 2028 | 52.8 MW |
| CARRADALE GRID (wind on) | 4 Jan 2024 | 30 Apr 2030 | 72.6 MW |
| CARRADALE GRID (bess) | 3 Apr 2024 | 31 Oct 2032 | 49.9 MW |
| CARRADALE (wind on) | 24 Oct 2023 | 31 Oct 2034 | 30 MW |
| CARRADALE GRID (wind on) | 25 Feb 2025 | 31 Oct 2034 | 60 MW |
| CARRADALE GRID (solar) | 30 May 2025 | 31 Oct 2034 | 4 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 102.86 MW |
| 2027 | 117.06 MW |
| 2028 | 219.86 MW |
| 2030 | 292.46 MW |
| 2032 | 342.36 MW |
| 2034 | 436.36 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | CARRADALE GRID (hydro) | 0.16 MW | 0 MW | 31 Jan 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | CARRADALE GRID (bess) | 49.9 MW | 0.16 MW | 8 Apr 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | CARRADALE GRID (wind on) | 52.8 MW | 50.06 MW | 30 Apr 2026 | not stated | gate not printed | Accepted to Connect |
| 4 | CARRADALE GRID (solar) | 14.2 MW | 102.86 MW | 22 May 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | CARRADALE GRID (wind on) | 50 MW | 117.06 MW | 31 May 2028 | not stated | gate not printed | Accepted to Connect |
| 6 | CARRADALE GRID (wind on) | 52.8 MW | 167.06 MW | 29 Sep 2028 | not stated | gate not printed | Accepted to Connect |
| 7 | CARRADALE GRID (wind on) | 72.6 MW | 219.86 MW | 30 Apr 2030 | not stated | gate not printed | Accepted to Connect |
| 8 | CARRADALE GRID (bess) | 49.9 MW | 292.46 MW | 31 Oct 2032 | not stated | gate not printed | Accepted to Connect |
| 9 | CARRADALE (wind on) | 30 MW | 342.36 MW | 31 Oct 2034 | not stated | gate not printed | Accepted to Connect |
| 10 | CARRADALE GRID (wind on) | 60 MW | 372.36 MW | 31 Oct 2034 | not stated | gate not printed | Accepted to Connect |
| 11 | CARRADALE GRID (solar) | 4 MW | 432.36 MW | 31 Oct 2034 | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 3 | 102.86 MW |
| 2027 | 1 | 14.2 MW |
| 2028 | 2 | 102.8 MW |
| 2030 | 1 | 72.6 MW |
| 2032 | 1 | 49.9 MW |
| 2034 | 3 | 94 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| CARRADALE GRID (onshore wind, 72.6 MW) | Onshore wind | 72.6 MW | 30 Apr 2030 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 60 MW) | Onshore wind | 60 MW | 31 Oct 2034 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 52.8 MW) | Onshore wind | 52.8 MW | 30 Apr 2026 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 52.8 MW) | Onshore wind | 52.8 MW | 29 Sep 2028 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 50 MW) | Onshore wind | 50 MW | 31 May 2028 | Accepted to Connect |
| CARRADALE GRID (battery, 49.9 MW) | Battery storage | 49.9 MW | 31 Oct 2032 | Accepted to Connect |
| CARRADALE GRID (battery, 49.9 MW) | Battery storage | 49.9 MW | 8 Apr 2026 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 47.5 MW) | Onshore wind | 47.5 MW | not stated | Connected |
| CARRADALE GRID (onshore wind, 43.7 MW) | Onshore wind | 43.7 MW | not stated | Connected |
| CARRADALE GRID (onshore wind, 33.25 MW) | Onshore wind | 33.25 MW | not stated | Connected |
| CARRADALE GRID (onshore wind, 30 MW) | Onshore wind | 30 MW | 31 Oct 2034 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 14.25 MW) | Onshore wind | 14.25 MW | not stated | Connected |
| CARRADALE GRID (onshore wind, 14.25 MW) | Onshore wind | 14.25 MW | not stated | Connected |
| CARRADALE GRID (onshore wind, 14.21 MW) | Onshore wind | 14.21 MW | not stated | Connected |
| CARRADALE GRID (solar, 14.2 MW) | Solar | 14.2 MW | 22 May 2027 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 6.55 MW) | Onshore wind | 6.56 MW | not stated | Connected |
| CARRADALE GRID (hydro, 1.14 MW) | Hydro and pumped storage | 1.14 MW | not stated | Connected |
| CARRADALE GRID (hydro, 0.16 MW) | Hydro and pumped storage | 0.16 MW | 31 Jan 2026 | Accepted to Connect |
| CARRADALE GRID (hydro, 0.1 MW) | Hydro and pumped storage | 0.1 MW | not stated | Connected |
| CARRADALE GRID (hydro, 0.1 MW) | Hydro and pumped storage | 0.1 MW | not stated | Connected |
| CARRADALE GRID (solar, 4 MW) | Solar | 0.1 MW | 31 Oct 2034 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 52.8 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |
| CARRADALE GRID (onshore wind, 26 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |
| CARRADALE GRID (onshore wind, 26 MW) | Onshore wind | 0 MW | 29 May 2036 | Accepted to Connect |
| CARRADALE GRID (hydro, 0.5 MW) | Hydro and pumped storage | 0 MW | not stated | Accepted to Connect |
| CARRADALE GRID (battery, 49.9 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| CARRADALE GRID (hydro, 0.16 MW) | Hydro and pumped storage | 0 MW | not stated | Accepted to Connect |
| CARRADALE GRID (hydro, 0.1 MW) | Hydro and pumped storage | 0 MW | not stated | Accepted to Connect |
| CARRADALE GRID (solar, 4 MW) | Solar | 0 MW | 31 Dec 2030 | Accepted to Connect |
| CARRADALE GRID (onshore wind, 72.6 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |