N84 Grid

CARRADALE GRID

DNO substation.

Contracted here0.44 GWNot yet connected, as printed
Entries in the queue11entries with a printed MW
Earliest connection date31 Jan 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue219.86 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
CARRADALE GRID (hydro)27 Nov 202431 Jan 20260.16 MW
CARRADALE GRID (bess)8 Apr 20258 Apr 202649.9 MW
CARRADALE GRID (wind on)11 Jan 202330 Apr 202652.8 MW
CARRADALE GRID (solar)22 Feb 202622 May 202714.2 MW
CARRADALE GRID (wind on)27 Jan 202031 May 202850 MW
CARRADALE GRID (wind on)14 Jul 202629 Sep 202852.8 MW
CARRADALE GRID (wind on)4 Jan 202430 Apr 203072.6 MW
CARRADALE GRID (bess)3 Apr 202431 Oct 203249.9 MW
CARRADALE (wind on)24 Oct 202331 Oct 203430 MW
CARRADALE GRID (wind on)25 Feb 202531 Oct 203460 MW
CARRADALE GRID (solar)30 May 202531 Oct 20344 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW250 MW500 MW2026: 103 MW2027: 117 MW2028: 220 MW2030: 292 MW2032: 342 MW2034: 436 MW20262028203020322034436 MW
0 MW250 MW500 MW2026: 103 MW2027: 117 MW2028: 220 MW2030: 292 MW2032: 342 MW2034: 436 MW2026202920322034436 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026102.86 MW
2027117.06 MW
2028219.86 MW
2030292.46 MW
2032342.36 MW
2034436.36 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1CARRADALE GRID (hydro)0.16 MW0 MW31 Jan 2026not statedgate not printedAccepted to Connect
2CARRADALE GRID (bess)49.9 MW0.16 MW8 Apr 2026not statedgate not printedAccepted to Connect
3CARRADALE GRID (wind on)52.8 MW50.06 MW30 Apr 2026not statedgate not printedAccepted to Connect
4CARRADALE GRID (solar)14.2 MW102.86 MW22 May 2027not statedgate not printedAccepted to Connect
5CARRADALE GRID (wind on)50 MW117.06 MW31 May 2028not statedgate not printedAccepted to Connect
6CARRADALE GRID (wind on)52.8 MW167.06 MW29 Sep 2028not statedgate not printedAccepted to Connect
7CARRADALE GRID (wind on)72.6 MW219.86 MW30 Apr 2030not statedgate not printedAccepted to Connect
8CARRADALE GRID (bess)49.9 MW292.46 MW31 Oct 2032not statedgate not printedAccepted to Connect
9CARRADALE (wind on)30 MW342.36 MW31 Oct 2034not statedgate not printedAccepted to Connect
10CARRADALE GRID (wind on)60 MW372.36 MW31 Oct 2034not statedgate not printedAccepted to Connect
11CARRADALE GRID (solar)4 MW432.36 MW31 Oct 2034not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20263102.86 MW
2027114.2 MW
20282102.8 MW
2030172.6 MW
2032149.9 MW
2034394 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
CARRADALE GRID (onshore wind, 72.6 MW)Onshore wind72.6 MW30 Apr 2030Accepted to Connect
CARRADALE GRID (onshore wind, 60 MW)Onshore wind60 MW31 Oct 2034Accepted to Connect
CARRADALE GRID (onshore wind, 52.8 MW)Onshore wind52.8 MW30 Apr 2026Accepted to Connect
CARRADALE GRID (onshore wind, 52.8 MW)Onshore wind52.8 MW29 Sep 2028Accepted to Connect
CARRADALE GRID (onshore wind, 50 MW)Onshore wind50 MW31 May 2028Accepted to Connect
CARRADALE GRID (battery, 49.9 MW)Battery storage49.9 MW31 Oct 2032Accepted to Connect
CARRADALE GRID (battery, 49.9 MW)Battery storage49.9 MW8 Apr 2026Accepted to Connect
CARRADALE GRID (onshore wind, 47.5 MW)Onshore wind47.5 MWnot statedConnected
CARRADALE GRID (onshore wind, 43.7 MW)Onshore wind43.7 MWnot statedConnected
CARRADALE GRID (onshore wind, 33.25 MW)Onshore wind33.25 MWnot statedConnected
CARRADALE GRID (onshore wind, 30 MW)Onshore wind30 MW31 Oct 2034Accepted to Connect
CARRADALE GRID (onshore wind, 14.25 MW)Onshore wind14.25 MWnot statedConnected
CARRADALE GRID (onshore wind, 14.25 MW)Onshore wind14.25 MWnot statedConnected
CARRADALE GRID (onshore wind, 14.21 MW)Onshore wind14.21 MWnot statedConnected
CARRADALE GRID (solar, 14.2 MW)Solar14.2 MW22 May 2027Accepted to Connect
CARRADALE GRID (onshore wind, 6.55 MW)Onshore wind6.56 MWnot statedConnected
CARRADALE GRID (hydro, 1.14 MW)Hydro and pumped storage1.14 MWnot statedConnected
CARRADALE GRID (hydro, 0.16 MW)Hydro and pumped storage0.16 MW31 Jan 2026Accepted to Connect
CARRADALE GRID (hydro, 0.1 MW)Hydro and pumped storage0.1 MWnot statedConnected
CARRADALE GRID (hydro, 0.1 MW)Hydro and pumped storage0.1 MWnot statedConnected
CARRADALE GRID (solar, 4 MW)Solar0.1 MW31 Oct 2034Accepted to Connect
CARRADALE GRID (onshore wind, 52.8 MW)Onshore wind0 MWnot statedAccepted to Connect
CARRADALE GRID (onshore wind, 26 MW)Onshore wind0 MWnot statedAccepted to Connect
CARRADALE GRID (onshore wind, 26 MW)Onshore wind0 MW29 May 2036Accepted to Connect
CARRADALE GRID (hydro, 0.5 MW)Hydro and pumped storage0 MWnot statedAccepted to Connect
CARRADALE GRID (battery, 49.9 MW)Battery storage0 MWnot statedAccepted to Connect
CARRADALE GRID (hydro, 0.16 MW)Hydro and pumped storage0 MWnot statedAccepted to Connect
CARRADALE GRID (hydro, 0.1 MW)Hydro and pumped storage0 MWnot statedAccepted to Connect
CARRADALE GRID (solar, 4 MW)Solar0 MW31 Dec 2030Accepted to Connect
CARRADALE GRID (onshore wind, 72.6 MW)Onshore wind0 MWnot statedAccepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.