The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- KINTORE GRID (wind on)
1 Aug 2025 to 1 Aug 2026, date already passed (gate not printed) - KINTORE (bess)
16 Jun 2021 to 31 Oct 2026 (gate not printed) - KINTORE (bess)
29 Sep 2021 to 30 Nov 2026 (gate not printed) - KINTORE GRID (wind on)
4 Jun 2026 to 4 Jun 2027 (gate not printed) - KINTORE GRID (wind on)
4 Jun 2026 to 31 Jul 2028 (gate not printed) - KINTORE GRID (other)
29 Sep 2023 to 30 Sep 2029 (gate not printed) - KINTORE GRID (bess)
10 Mar 2022 to 31 Oct 2031 (gate not printed) - KINTORE GRID (other)
6 Jul 2021 to 19 May 2032 (gate not printed) - KINTORE GRID (solar)
7 Jul 2025 to 7 Jul 2032 (gate not printed) - KINTORE GRID (wind on)
30 Nov 2022 to 28 Feb 2033 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| KINTORE GRID (wind on) | 1 Aug 2025 | 1 Aug 2026 | 4.1 MW |
| KINTORE (bess) | 16 Jun 2021 | 31 Oct 2026 | 50 MW |
| KINTORE (bess) | 29 Sep 2021 | 30 Nov 2026 | 49.9 MW |
| KINTORE GRID (wind on) | 4 Jun 2026 | 4 Jun 2027 | 0.8 MW |
| KINTORE GRID (wind on) | 4 Jun 2026 | 31 Jul 2028 | 0.2 MW |
| KINTORE GRID (other) | 29 Sep 2023 | 30 Sep 2029 | 20 MW |
| KINTORE GRID (bess) | 10 Mar 2022 | 31 Oct 2031 | 49.9 MW |
| KINTORE GRID (other) | 6 Jul 2021 | 19 May 2032 | 55 MW |
| KINTORE GRID (solar) | 7 Jul 2025 | 7 Jul 2032 | 22 MW |
| KINTORE GRID (wind on) | 30 Nov 2022 | 28 Feb 2033 | 4.5 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 104 MW |
| 2027 | 104.8 MW |
| 2028 | 105 MW |
| 2029 | 125 MW |
| 2031 | 174.9 MW |
| 2032 | 251.9 MW |
| 2033 | 256.4 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | KINTORE GRID (wind on) | 4.1 MW | 0 MW | 1 Aug 2026 | not stated | gate not printed | Accepted to Connect |
| 2 | KINTORE (bess) | 50 MW | 4.1 MW | 31 Oct 2026 | not stated | gate not printed | Accepted to Connect |
| 3 | KINTORE (bess) | 49.9 MW | 54.1 MW | 30 Nov 2026 | not stated | gate not printed | Accepted to Connect |
| 4 | KINTORE GRID (wind on) | 0.8 MW | 104 MW | 4 Jun 2027 | not stated | gate not printed | Accepted to Connect |
| 5 | KINTORE GRID (wind on) | 0.2 MW | 104.8 MW | 31 Jul 2028 | not stated | gate not printed | Accepted to Connect |
| 6 | KINTORE GRID (other) | 20 MW | 105 MW | 30 Sep 2029 | not stated | gate not printed | Accepted to Connect |
| 7 | KINTORE GRID (bess) | 49.9 MW | 125 MW | 31 Oct 2031 | not stated | gate not printed | Accepted to Connect |
| 8 | KINTORE GRID (other) | 55 MW | 174.9 MW | 19 May 2032 | not stated | gate not printed | Accepted to Connect |
| 9 | KINTORE GRID (solar) | 22 MW | 229.9 MW | 7 Jul 2032 | not stated | gate not printed | Accepted to Connect |
| 10 | KINTORE GRID (wind on) | 4.5 MW | 251.9 MW | 28 Feb 2033 | not stated | gate not printed | Accepted to Connect |
| 11 | KINTORE GRID (solar) | 0.57 MW | 256.4 MW | not stated | not stated | gate not printed | Accepted to Connect |
Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 3 | 104 MW |
| 2027 | 1 | 0.8 MW |
| 2028 | 1 | 0.2 MW |
| 2029 | 1 | 20 MW |
| 2031 | 1 | 49.9 MW |
| 2032 | 2 | 77 MW |
| 2033 | 1 | 4.5 MW |
| not stated | 1 | 0.57 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| KINTORE GRID (battery, 50 MW) | Battery storage | 50 MW | 31 Oct 2026 | Accepted to Connect |
| KINTORE GRID (battery, 49.9 MW) | Battery storage | 49.9 MW | 31 Oct 2031 | Accepted to Connect |
| KINTORE GRID (battery, 49.9 MW) | Battery storage | 49.9 MW | 30 Nov 2026 | Accepted to Connect |
| KINTORE GRID (battery, 47.49 MW) | Battery storage | 47.49 MW | not stated | Connected |
| KINTORE GRID (other, 55 MW) | Other | 40 MW | 19 May 2032 | Accepted to Connect |
| KINTORE GRID (solar, 22 MW) | Solar | 22 MW | 7 Jul 2032 | Accepted to Connect |
| KINTORE GRID (other, 20 MW) | Other | 20 MW | 30 Sep 2029 | Accepted to Connect |
| KINTORE GRID (onshore wind, 12.5 MW) | Onshore wind | 12.5 MW | not stated | Connected |
| KINTORE GRID (hybrid, 8.75 MW) | Hybrid | 8.75 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 6.55 MW) | Onshore wind | 6.56 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 4.5 MW) | Onshore wind | 4.5 MW | 28 Feb 2033 | Accepted to Connect |
| KINTORE GRID (onshore wind, 4.37 MW) | Onshore wind | 4.37 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 4.1 MW) | Onshore wind | 4.1 MW | 1 Aug 2026 | Accepted to Connect |
| KINTORE GRID (onshore wind, 2.28 MW) | Onshore wind | 2.28 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 2.28 MW) | Onshore wind | 2.28 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 2.19 MW) | Onshore wind | 2.19 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 2.19 MW) | Onshore wind | 2.19 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 2.19 MW) | Onshore wind | 2.19 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 0.8 MW) | Onshore wind | 0.8 MW | 4 Jun 2027 | Accepted to Connect |
| KINTORE GRID (other, 0.45 MW) | Other | 0.45 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 0.33 MW) | Onshore wind | 0.33 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 0.31 MW) | Onshore wind | 0.31 MW | not stated | Connected |
| KINTORE GRID (other, 0.42 MW) | Other | 0.19 MW | not stated | Connected |
| KINTORE GRID (onshore wind, 0.2 MW) | Onshore wind | 0 MW | 31 Jul 2028 | Accepted to Connect |
| KINTORE GRID (onshore wind, 4.5 MW) | Onshore wind | 0 MW | not stated | Accepted to Connect |
| KINTORE GRID (onshore wind, 0.8 MW) | Onshore wind | 0 MW | 4 Jun 2027 | Accepted to Connect |
| KINTORE GRID (battery, 49.99 MW) | Battery storage | 0 MW | not stated | Accepted to Connect |
| KINTORE GRID (solar, 0.57 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| KINTORE GRID (other, 36.8 MW) | Other | 0 MW | not stated | Accepted to Connect |
| KINTORE GRID (onshore wind, 0.8 MW) | Onshore wind | 0 MW | 6 Apr 2027 | Accepted to Connect |
| KINTORE GRID (solar, 10 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| KINTORE GRID (solar, 0.03 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| KINTORE GRID (solar, 23.86 MW) | Solar | 0 MW | not stated | Accepted to Connect |
| KINTORE GRID (onshore wind, 0.2 MW) | Onshore wind | 0 MW | 31 Jul 2028 | Accepted to Connect |
| KINTORE GRID (solar, 8.75 MW) | Solar | 0 MW | 3 Sep 2026 | Accepted to Connect |
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.