N84 Grid

NURSLING GSP

DNO substation.

Contracted here0.87 GWNot yet connected, as printed
Entries in the queue9entries with a printed MW
Earliest connection date28 Mar 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue721.3 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
NURSLING GSP (solar)29 Apr 202428 Mar 202540 MW
NURSLING GSP (bess)7 Aug 20233 Dec 202650 MW
NURSLING GSP (solar)26 Mar 202131 Jan 202932.4 MW
NURSLING (hybrid)2 Jun 202630 Dec 2031450 MW
NURSLING GSP (bess)11 Feb 202231 Dec 203649.9 MW
NURSLING (bess)4 Jan 202331 Dec 203699 MW
NURSLING GSP (hybrid)30 Aug 202430 Oct 203749.9 MW
NURSLING GSP (bess)7 Jul 202231 Oct 203749.9 MW
NURSLING GSP (other)4 Dec 202331 Oct 203750 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2025: 40 MW2026: 90 MW2029: 122 MW2031: 572 MW2036: 721 MW2037: 871 MW2025202720292031203320352037871 MW
0 MW500 MW1.0 GW2025: 40 MW2026: 90 MW2029: 122 MW2031: 572 MW2036: 721 MW2037: 871 MW2025202920332037871 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202540 MW
202690 MW
2029122.4 MW
2031572.4 MW
2036721.3 MW
2037871.1 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1NURSLING GSP (solar)40 MW0 MW28 Mar 2025not statedgate not printedAccepted to Connect
2NURSLING GSP (bess)50 MW40 MW3 Dec 2026not statedgate not printedAccepted to Connect
3NURSLING GSP (solar)32.4 MW90 MW31 Jan 2029not statedgate not printedAccepted to Connect
4NURSLING (hybrid)450 MW122.4 MW30 Dec 2031not statedgate not printedAccepted to Connect
5NURSLING GSP (bess)49.9 MW572.4 MW31 Dec 2036not statedgate not printedAccepted to Connect
6NURSLING (bess)99 MW622.3 MW31 Dec 2036not statedgate not printedAccepted to Connect
7NURSLING GSP (hybrid)49.9 MW721.3 MW30 Oct 2037not statedgate not printedAccepted to Connect
8NURSLING GSP (bess)49.9 MW771.2 MW31 Oct 2037not statedgate not printedAccepted to Connect
9NURSLING GSP (other)50 MW821.1 MW31 Oct 2037not statedgate not printedAccepted to Connect

Receipt: MW and dates as printed in the SSEN Embedded Capacity Register, file dated 1 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025140 MW
2026150 MW
2029132.4 MW
20311450 MW
20362148.9 MW
20373149.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
NURSLING GSP (hybrid, 450 MW)Hybrid200 MW30 Dec 2031Accepted to Connect
NURSLING GSP (battery, 99 MW)Battery storage99 MW31 Dec 2036Accepted to Connect
NURSLING GSP (other, 50 MW)Other50 MW31 Oct 2037Accepted to Connect
NURSLING GSP (battery, 50 MW)Battery storage50 MW3 Dec 2026Accepted to Connect
NURSLING GSP (battery, 49.9 MW)Battery storage49.9 MW31 Dec 2036Accepted to Connect
NURSLING GSP (battery, 49.9 MW)Battery storage49.9 MW31 Oct 2037Accepted to Connect
NURSLING GSP (hybrid, 49.9 MW)Hybrid49.9 MW30 Oct 2037Accepted to Connect
NURSLING GSP (solar, 40 MW)Solar40 MW28 Mar 2025Accepted to Connect
NURSLING GSP (solar, 32.4 MW)Solar32.4 MW31 Jan 2029Accepted to Connect
NURSLING GSP (solar, 0.17 MW)Solar0.17 MWnot statedConnected
NURSLING GSP (other, 0.16 MW)Other0.16 MWnot statedConnected
NURSLING GSP (other, 0.06 MW)Other0.06 MWnot statedConnected
NURSLING GSP (other, 0.33 MW)Other0.06 MWnot statedConnected
NURSLING GSP (battery, 50 MW)Battery storage0 MWnot statedAccepted to Connect
NURSLING GSP (other, 50 MW)Other0 MWnot statedAccepted to Connect
NURSLING GSP (battery, 99 MW)Battery storage0 MWnot statedAccepted to Connect
NURSLING GSP (hybrid, 300 MW)Hybrid0 MWnot statedAccepted to Connect
NURSLING GSP (solar, 20 MW)Solar0 MWnot statedAccepted to Connect
NURSLING GSP (battery, 54 MW)Battery storage0 MW31 Dec 2036Accepted to Connect
NURSLING GSP (hybrid, 450 MW)Hybrid0 MW30 Dec 2031Accepted to Connect

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.