BAYWA R.E. UK LIMITED

Grouped by published name, unverified. Printed as: BAYWA R.E. UK LIMITED.

Sign in to watch this developer
6Projects in the shown registers
1,180.5 MWTotal MW as printed
0 / 1Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 1.2 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued1.2
MW by technology
TechnologyProjectsMW
Battery storage3713 MW
Hybrid3467.5 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Caithness Energy Storage (BAYWA R.E. UK LIMITED)Battery storage456 MW31 Oct 2034ScopingCAITHNESS ENERGY STORAGE 400KV SUBSTATION
Bernicia Energy ParkHybrid350 MW30 Oct 2035ScopingStella West 400kV Substation
Longside BESSBattery storage200 MW31 Oct 2033ScopingPeterhead 2 400kV Busbar Extension
Tinnisburn Wind Farm (BAYWA R.E. UK LIMITED)Hybrid70 MW31 Oct 2031ScopingTINNISBURN WIND FARM 132KV SUBSTATION
Norton (BAYWA R.E. UK LIMITED)Battery storage57 MW1 Jun 2029Awaiting ConsentsNorton GSP
Mannington (BAYWA R.E. UK LIMITED)Hybrid47.5 MW28 Apr 2028ScopingMannington 400kV Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.