YEOVIL (solar, 9 MW)

Developer as published, connection site, reference: YEOVIL. SSEN-1MW-5f01bfcbd8f2.

Sign in to watch this project
Capacity9 MWSolar
Connection date7 Oct 2026Status as printed: Accepted to Connect
First date seen 6 Dec 2024, difference +670 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

20262027File dated 2025-03-01: connection date 2026-10-07Oct 2026File dated 2026-10-01: connection date 2026-10-071 Mar20251 Oct2026
20262027File dated 2025-03-01: connection date 2026-10-07Oct 2026File dated 2026-10-01: connection date 2026-10-071 Mar20251 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 1 Mar 2025 to 1 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.