Willington Energy Park

Developer as published, connection site, reference: BROCKWELL STORAGE & SOLAR LIMITED. Willington 400kV Substation (NGET). PRO-001964.

Sign in to watch this project
Capacity500 MWHybrid
Connection date31 Oct 2028Status as printed: Scoping
First date seen 30 Mar 2028, difference +215 dayscalculated by N84
MW ahead in N84's order at this site400 MWcalculated by N84

Connection date, edition by edition

20282029File dated 2026-09-11: connection date 2028-03-30Mar 2028File dated 2026-10-20: connection date 2028-10-31Oct 202811 Sep202620 Oct2026
20282029File dated 2026-09-11: connection date 2028-03-30Mar 2028File dated 2026-10-20: connection date 2028-10-31Oct 202811 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Oct 2028 (previous file: 30 Mar 2028), 215 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +215 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 2167Receipt: NESO TEC Register, file dated 11 Sep 2026, row 2138

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.