5Projects in the shown registers
1,420 MWTotal MW as printed
2 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 1.4 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 1.4 |
| Technology | Projects | MW |
|---|---|---|
| Hybrid | 2 | 1,000 MW |
| Battery storage | 3 | 420 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Eaton Socon Solar | Hybrid | 500 MW | 31 Oct 2028 | Scoping | Eaton Socon 400kV Substation |
| Willington Energy Park | Hybrid | 500 MW | 31 Oct 2028 | Scoping | Willington 400kV Substation |
| Didcot Energy Park | Battery storage | 300 MW | 31 Oct 2027 | Awaiting Consents | Didcot 400kV Substation |
| Inchbean Energy Park | Battery storage | 60 MW | 8 Feb 2027 | Consents Approved | Kilmarnock Town 275/33kV Substation |
| Longriggs Energy Park | Battery storage | 60 MW | 30 Apr 2039 | Awaiting Consents | Devonside 132/33kV |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.