N84 Grid

BROCKWELL STORAGE & SOLAR LIMITED

Grouped by published name, unverified. Printed as: BROCKWELL STORAGE & SOLAR LIMITED.

Sign in to watch this developer
5Projects in the shown registers
1,420 MWTotal MW as printed
2 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 1.4 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued1.4
MW by technology
TechnologyProjectsMW
Hybrid21,000 MW
Battery storage3420 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Eaton Socon SolarHybrid500 MW31 Oct 2028ScopingEaton Socon 400kV Substation
Willington Energy ParkHybrid500 MW31 Oct 2028ScopingWillington 400kV Substation
Didcot Energy ParkBattery storage300 MW31 Oct 2027Awaiting ConsentsDidcot 400kV Substation
Inchbean Energy ParkBattery storage60 MW8 Feb 2027Consents ApprovedKilmarnock Town 275/33kV Substation
Longriggs Energy ParkBattery storage60 MW30 Apr 2039Awaiting ConsentsDevonside 132/33kV

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.