Willington 400kV Substation

NESO connection site, host NGET.

Contracted here2.13 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,125 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Willington Green Energy Centre31 May 202430 Oct 2028400 MW
Willington Energy Park31 May 202431 Oct 2028500 MW
Willington31 May 202430 Oct 2029600 MW
Willington Green Energy Centre31 May 202430 Oct 2031625 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2028: 900 MW2029: 1.5 GW2031: 2.1 GW20282029203020312.1 GW
0 MW1.3 GW2.5 GW2028: 900 MW2029: 1.5 GW2031: 2.1 GW20282029203020312.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028900 MW
20291,500 MW
20312,125 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Willington Green Energy Centre400 MW0 MW30 Oct 2028not statedgate not printedScoping
2Willington Energy Park500 MW400 MW31 Oct 2028not statedgate not printedScoping
3Willington600 MW900 MW30 Oct 20291gate 1Scoping
4Willington Green Energy Centre625 MW1,500 MW30 Oct 2031not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20282900 MW
20291600 MW
20311625 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Willington Green Energy CentreHybrid1,025 MW30 Oct 2031Awaiting Consents
Willington (SSE UTILITY SOLUTIONS LIMITED)Hybrid600 MW30 Oct 2029Scoping
Willington Energy ParkHybrid500 MW31 Oct 2028Scoping
DerwentGas162 MW1 Apr 2024Built
Trafalgar ParkThermal14 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.