Alverdiscott (PIVOTED POWER LLP)

Developer as published, connection site, reference: PIVOTED POWER LLP. Alverdiscott 400kV Substation (NGET). PRO-001136.

Sign in to watch this project
Capacity100 MWBattery storage, Gate 1
Connection date31 Oct 2036Status as printed: Scoping
First date seen 31 Oct 2029, difference +2557 dayscalculated by N84
MW ahead in N84's order at this site2,100 MWcalculated by N84

Connection date, edition by edition

2029203020312032File dated 2026-09-11: connection date 2029-10-31Oct 2029File dated 2026-10-20: connection date 2031-08-31Aug 203111 Sep202620 Oct2026
2029203020312032File dated 2026-09-11: connection date 2029-10-31Oct 2029File dated 2026-10-20: connection date 2031-08-31Aug 203111 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 31 Aug 2031 (previous file: 31 Oct 2029), 669 days later. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. +669 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 56Receipt: NESO TEC Register, file dated 11 Sep 2026, row 56

Supported by National Energy SO Open Data