Teeside MPI

Developer as published, connection site, reference: National Grid Interconnector Holdings Limited. Wearside Connection Node B 400kV Substation (NGET). PRO-003462.

Sign in to watch this project
Capacity1,800 MWInterconnector, Gate 1
Connection date30 Oct 2035Status as printed: Scoping
First date seen 31 Oct 2033, difference +729 dayscalculated by N84
MW ahead in N84's order at this site0 MWcalculated by N84

Connection date, edition by edition

2033203420352036File dated 2025-07-22: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2035-10-30Oct 203522 Jul202520 Oct2026
2033203420352036File dated 2025-07-22: connection date 2033-10-31Oct 2033File dated 2026-10-20: connection date 2035-10-30Oct 203522 Jul202520 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. Gate printed as 1 (previous file: blank). N84 holds no copy between 22 Jul 2025 and 20 Oct 2026; this change happened at some point in that time. Wide comparison Correction after an older file was importedblank → 1Receipt: NESO Interconnector Register, file dated 20 Oct 2026, row 33Receipt: NESO Interconnector Register, file dated 22 Jul 2025, row 31
  2. 20 Oct 2026. MW Effective From printed as 30 Oct 2035 (previous file: 31 Oct 2033), 729 days later. N84 holds no copy between 22 Jul 2025 and 20 Oct 2026; this change happened at some point in that time. +729 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO Interconnector Register, file dated 20 Oct 2026, row 33Receipt: NESO Interconnector Register, file dated 22 Jul 2025, row 31

Supported by National Energy SO Open Data