Field Farm

Developer as published, connection site, reference: Net Zero One Ltd. Staythorpe 400kV Substation (NGET). PRO-001924.

Sign in to watch this project
Capacity249.9 MWBattery storage, Gate 1
Connection date30 Sep 2030Status as printed: Scoping
First date seen 31 Oct 2030, difference -31 dayscalculated by N84
MW ahead in N84's order at this site1,237 MWcalculated by N84

Connection date, edition by edition

20302031File dated 2026-09-11: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2030-09-30Sep 203011 Sep202620 Oct2026
20302031File dated 2026-09-11: connection date 2030-10-31Oct 2030File dated 2026-10-20: connection date 2030-09-30Sep 203011 Sep202620 Oct2026

Each step is a file that printed the connection date differently from the file before it. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

  1. 20 Oct 2026. MW Effective From printed as 30 Sep 2030 (previous file: 31 Oct 2030), 31 days earlier. N84 holds no copy between 11 Sep 2026 and 20 Oct 2026; this change happened at some point in that time. -31 dayscalculated by N84 Wide comparison Correction after an older file was importedReceipt: NESO TEC Register, file dated 20 Oct 2026, row 803Receipt: NESO TEC Register, file dated 11 Sep 2026, row 782

Supported by National Energy SO Open Data