N84 Grid

Net Zero One Ltd

Grouped by published name, unverified. Printed as: Net Zero One Limited; Net Zero One Ltd.

Sign in to watch this developer
3Projects in the shown registers
1,999.8 MWTotal MW as printed
0 / 1Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 2.0 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued2.0
MW by technology
TechnologyProjectsMW
Hybrid11,500 MW
Battery storage2499.8 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Old Flatts FarmHybrid1,500 MW30 Oct 2035ScopingBrinsworth 400kV Substation
Field FarmBattery storage249.9 MW30 Sep 2030ScopingStaythorpe 400kV Substation
Penketh Hall FarmBattery storage249.9 MW1 Sep 2027ScopingFiddlers Ferry 275kV Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.