N84 Grid

Continental Link

Developer as published, connection site, reference: National Grid Interconnector Holdings Limited. Birkhill Wood 400kV Substation (NGET). PRO-000977.

Sign in to watch this project
Capacity1,800 MWInterconnector
Connection date31 Oct 2035Status as printed: Scoping
First date seen 1 Sep 2027, difference +2982 dayscalculated by N84
MW ahead in N84's order at this site5,350 MWcalculated by N84

Connection date, edition by edition

20352036File dated 2022-02-15: connection date 2035-10-31Oct 2035File dated 2026-10-20: connection date 2035-10-3115 Feb202220 Oct2026
20352036File dated 2022-02-15: connection date 2035-10-31Oct 2035File dated 2026-10-20: connection date 2035-10-3115 Feb202220 Oct2026

The connection date is printed the same in every file N84 holds for this project, from 15 Feb 2022 to 20 Oct 2026. Year marks on the side are 1 January.

Observed changes

Showing changes in files dated from 23 Sep 2026.

No changes observed in the files N84 holds for this window.

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.