N84 Grid

Birkhill Wood 400kV Substation

NESO connection site, host NGET.

Contracted here7.15 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date30 Oct 2030Date printed in the register

The queue, in order

Order calculated by N84
First in queue5,350 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Dogger Bank South East31 May 202430 Oct 2030400 MW
Dogger Bank South West31 May 202430 Oct 2030400 MW
Dogger Bank D Offshore Wind Farm31 May 202431 Oct 20311,450 MW
Dogger Bank South East31 May 202430 Nov 20311,050 MW
Dogger Bank South West31 May 202430 Nov 20311,050 MW
The Superconnection15 Feb 202228 Oct 20321,000 MW
Continental Link15 Feb 202231 Oct 20351,800 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW4.0 GW8.0 GW2030: 800 MW2031: 4.4 GW2032: 5.4 GW2035: 7.2 GW2030203120322033203420357.2 GW
0 MW4.0 GW8.0 GW2030: 800 MW2031: 4.4 GW2032: 5.4 GW2035: 7.2 GW20302032203420357.2 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2030800 MW
20314,350 MW
20325,350 MW
20357,150 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Dogger Bank South East400 MW0 MW30 Oct 2030not statedgate not printedScoping
2Dogger Bank South West400 MW400 MW30 Oct 2030not statedgate not printedScoping
3Dogger Bank D Offshore Wind Farm1,450 MW800 MW31 Oct 2031not statedgate not printedScoping
4Dogger Bank South East1,050 MW2,250 MW30 Nov 2031not statedgate not printedScoping
5Dogger Bank South West1,050 MW3,300 MW30 Nov 2031not statedgate not printedScoping
6The Superconnection1,000 MW4,350 MW28 Oct 20321gate 1Scoping
7Continental Link1,800 MW5,350 MW31 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Interconnector Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20302800 MW
203133,550 MW
203211,000 MW
203511,800 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Continental LinkInterconnector1,800 MW31 Oct 2035Scoping
Dogger Bank South West (was Irish Sea)Offshore wind1,450 MW30 Nov 2031Scoping
Dogger Bank D Offshore Wind FarmOffshore wind1,450 MW31 Oct 2031Scoping
North SeaOffshore wind1,450 MW30 Nov 2031Scoping
The SuperconnectionInterconnector1,000 MW28 Oct 2032Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.