6Projects in the shown registers
654.8 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 0.7 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 0.7 |
| Technology | Projects | MW |
|---|---|---|
| Battery storage | 6 | 654.8 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Bendle Farm 2.0 (Balance Power Projects Limited) | Battery storage | 228 MW | 31 Oct 2031 | Scoping | BENDLE FARM 2.0 132KV SUBSTATION |
| Bendle Farm (Balance Power Projects Limited) | Battery storage | 228 MW | 31 Oct 2031 | Scoping | Bendle Farm 132kV Substation |
| Hallyburton BESS | Battery storage | 49.9 MW | 31 Oct 2029 | Scoping | Coupar Angus 2 GSP |
| Hallyburton (2) | Battery storage | 49.9 MW | 31 Oct 2029 | Scoping | Coupar Angus 2 GSP |
| Cairnbulg BESS | Battery storage | 49.5 MW | 31 Oct 2033 | Scoping | Fraserburgh GSP |
| Backmuir Farm BESS | Battery storage | 49.5 MW | 31 Oct 2033 | Scoping | Blackhillock 2 400/33kV GSP Substation |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.