4Projects in the shown registers
4,000 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 4.0 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 4.0 |
| Technology | Projects | MW |
|---|---|---|
| Offshore wind | 3 | 3,000 MW |
| Battery storage | 1 | 1,000 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Icewind Connah's Quay | Offshore wind | 1,000 MW | 1 Nov 2033 | Scoping | Connah's Quay 400kV Substation |
| Icewind Hawthorn Pit | Offshore wind | 1,000 MW | 31 Oct 2031 | Scoping | Hawthorn Pit 400kV Substation |
| Icewind Hinkley Point | Battery storage | 1,000 MW | 31 Oct 2030 | Scoping | Woolavington 400kV Substation |
| Icewind Blyth | Offshore wind | 1,000 MW | 31 Oct 2031 | Scoping | Blyth 400kV Substation |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.