N84 Grid

FIELD DEVCO LTD

Grouped by published name, unverified. Printed as: FIELD DEVCO LTD.

Sign in to watch this developer
5Projects in the shown registers
950 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 1.0 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued1.0
MW by technology
TechnologyProjectsMW
Battery storage5950 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Broadford BESSBattery storage200 MW31 Oct 2034ScopingBroadford GSP
Field Glenniston BESS (FIELD DEVCO LTD)Battery storage200 MW29 Oct 2032ScopingFIELD GLENNISTON BESS 132KV SUBSTATION
Fort Augustus BESSBattery storage200 MW31 Oct 2035ScopingFort Augustus GSP
Dounreay BESSBattery storage200 MW31 Oct 2034ScopingNew Dounreay 400kV substation
Whitson BESSBattery storage150 MW30 Oct 2037ScopingWhitson 275kV Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.