6Projects in the shown registers
783 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 0.8 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued0.8
MW by technology
TechnologyProjectsMW
Battery storage5720 MW
Solar163 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
AGS Calderside Battery Energy Storage SystemBattery storage500 MW31 Oct 2033ScopingAGS CALDERSIDE 275KV SUBSTATION
AGS Calderside PV SolarSolar63 MW31 May 2027ScopingClydesmill 275/33kV
AGS CoatbridgeBattery storage60 MW30 Apr 2033ScopingCoatbridge GSP
AGS Nerston 2 BESSBattery storage55 MW31 Oct 2033ScopingEast Kilbride B 275/33kV Substation
AGS Nerston 3 BESSBattery storage55 MW31 Oct 2033ScopingEast Kilbride B 275/33kV Substation
AGS Nerston BESSBattery storage50 MW31 Oct 2033ScopingEast Kilbride B 275/33kV Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.