5Projects in the shown registers
1,580 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 1.6 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 1.6 |
| Technology | Projects | MW |
|---|---|---|
| Battery storage | 2 | 960 MW |
| Hybrid | 2 | 320 MW |
| Solar | 1 | 300 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Pamber Farm | Battery storage | 480 MW | 31 Oct 2037 | Awaiting Consents | Bramley 400kV Substation |
| Melkshem (Cartridge Farm) | Battery storage | 480 MW | 31 Oct 2037 | Awaiting Consents | Melksham 400kV Substation |
| Castlemilk 1 (Queequeg Renewables Ltd) | Solar | 300 MW | 31 Oct 2036 | Scoping | Castlemilk 400kV Substation |
| Apley Head Farm | Hybrid | 240 MW | 30 Oct 2035 | Scoping | Trent Valley South Connection Node B 400kV Substation. |
| Chesters | Hybrid | 80 MW | 29 Oct 2033 | Scoping | Teviot 400/132kV Substation |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.