7Projects in the shown registers
689 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
1Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 0.7 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 0.7 |
| Technology | Projects | MW |
|---|---|---|
| Hybrid | 6 | 674 MW |
| Onshore wind | 1 | 15 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Lincolnshire Energy Park | Hybrid | 500 MW | 30 Oct 2039 | Scoping | South Humber Connection Node A 400kV |
| Gwynt Alwen WF | Hybrid | 108 MW | 31 Oct 2032 | Scoping | North Wales connection Node A 400kV Substation |
| Brae WF | Hybrid | 20 MW | 30 Aug 2032 | Scoping | Linnmill GSP |
| Girlsta | Hybrid | 18 MW | 30 Sep 2029 | Scoping | Gremista GSP |
| Swarclett Farm and BESS | Hybrid | 18 MW | 31 Oct 2033 | Scoping | THURSO 2 275/33KV GRID SUPPLY POINT SUBSTATION |
| Stoneyfield | Onshore wind | 15 MW | 30 Sep 2030 | Scoping | Rothienorman GSP |
| Cairntawie | Hybrid | 10 MW | 31 Oct 2033 | Scoping | St Fergus Gas GSP |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.