9Projects in the shown registers
3,599.6 MWTotal MW as printed
3 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 3.6 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 3.6 |
| Technology | Projects | MW |
|---|---|---|
| Battery storage | 6 | 2,349.6 MW |
| Hybrid | 3 | 1,250 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Didcot BESS 1 | Battery storage | 750 MW | 31 Oct 2037 | Scoping | Chiltern Connection Node A 400kV Substation |
| FCC Thurcroft BESS | Battery storage | 750 MW | 31 Oct 2033 | Scoping | Leeds North Connection Node C 400kV Substation |
| Rat Hall Mod App | Hybrid | 700 MW | 31 Oct 2034 | Scoping | South Anglia Connection Node C 400kV Substation |
| Caegarw Farm | Hybrid | 350 MW | 10 May 2037 | Scoping | Margam B 400kV Substation |
| Ashbrook Lane BESS | Battery storage | 249.9 MW | 31 Oct 2034 | Scoping | WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION |
| Monk Fryston (Downing Renewable Developments LLP) | Battery storage | 249.9 MW | 30 Oct 2035 | Scoping | Monk Fryston 275kV Substation |
| Jackdaw BESS | Battery storage | 249.9 MW | 31 Oct 2036 | Scoping | Leeds North Connection Node B 400kV Substation |
| Rat Hall Solar | Hybrid | 200 MW | 31 Oct 2032 | Scoping | Burwell South 400kV Substation |
| Didcot BESS 2 | Battery storage | 99.9 MW | 31 Oct 2037 | Scoping | Didcot 132kV GIS Substation |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.