9Projects in the shown registers
3,600 MWTotal MW as printed
0 / 0Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025
Built and queued
Capacity already connected against capacity still waiting
- Queued: 3.6 GW (100%)
Table view
| Part | GW |
|---|---|
| Built | 0.0 |
| Queued | 3.6 |
| Technology | Projects | MW |
|---|---|---|
| Hybrid | 9 | 3,600 MW |
| Project (as published) | Technology | MW | Current date | Status (as printed) | Connection site |
|---|---|---|---|---|---|
| Exeter Main | Hybrid | 400 MW | 28 Oct 2033 | Scoping | Exeter 400kV Substation |
| Staythorpe (ENSO GREEN HOLDINGS X LIMITED) | Hybrid | 400 MW | 31 Oct 2030 | Scoping | Staythorpe 400kV Substation |
| Cilfynydd (ENSO GREEN HOLDINGS X LIMITED) | Hybrid | 400 MW | 31 Oct 2030 | Awaiting Consents | Cilfynydd 400kV Substation |
| Pelham 400 | Hybrid | 400 MW | 31 Oct 2034 | Scoping | West Anglia Connection Node E 400kV Substation |
| Long Stratton 400 | Hybrid | 400 MW | 31 Oct 2034 | Scoping | North Anglia Connection Node A 400kV |
| Cellarhead (ENSO GREEN HOLDINGS X LIMITED) | Hybrid | 400 MW | 31 Oct 2033 | Scoping | Cellarhead 400kV Substation |
| Norton | Hybrid | 400 MW | 31 Oct 2032 | Scoping | Norton East 400kV Substation |
| Feckenham (ENSO GREEN HOLDINGS X LIMITED) | Hybrid | 400 MW | 31 Oct 2036 | Awaiting Consents | Feckenham 400kV Substation |
| Monk Fryston (ENSO GREEN HOLDINGS X LIMITED) | Hybrid | 400 MW | 31 Oct 2031 | Scoping | Monk Fryston 275kV Substation |
Counts of what the registers printed. No score and no rank.
Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.