14Projects in the shown registers
2,194.41 MWTotal MW as printed
0 / 1Dates later / earlier, files since 23 Oct 2025
0Removed from the register, files since 23 Oct 2025

Built and queued

Capacity already connected against capacity still waiting

  • Queued: 2.2 GW (100%)
As printed in the shown registers; built is capacity the registers print as connected.
Table view
Built and queued
PartGW
Built0.0
Queued2.2
MW by technology
TechnologyProjectsMW
Battery storage111,503.66 MW
Solar3690.75 MW
Projects
Project (as published)TechnologyMWCurrent dateStatus (as printed)Connection site
Kenwick SolarSolar430.85 MW30 Oct 2037ScopingShrewsbury 400kV Substation
Overton Grange BESSBattery storage300 MW30 Oct 2035ScopingWearside Connection Node D 400kV Substation
Stirling BESSBattery storage300 MW31 Oct 2033ScopingPeterhead 400kV Substation
Redhall BESSBattery storage300 MW30 Oct 2035ScopingWearside Connection Node D 400kV Substation
BlackDyke BESSBattery storage250 MW31 Oct 2035ScopingLeeds North Connection Node D 400kV Substation
Derwent Solar PV ArraySolar160 MW31 May 2032ScopingThornton 400kV Substation
High Marnham Solar FarmSolar99.9 MW31 Oct 2031ScopingHigh Marnham 400kV Substation
Rothienorman 3 BESSBattery storage66 MW30 Jun 2030ScopingRothienorman 2 400/33KV GSP Substation
Nairn II BESSBattery storage65 MW31 Oct 2028ScopingNairn 132/33kV Grid Supply Point Substation
Persley BESSBattery storage63.3 MW31 Jul 2027Consents ApprovedPersley 132/33kV GSP Substation
Fettereso BESSBattery storage50 MW31 Oct 2028ScopingFettersso 132/33kV Grid Supply Point Substation
Keith BESSBattery storage50 MW31 Oct 2033ScopingBlackhillock 2 400/33kV GSP Substation
Mybster BESS_Ver2Battery storage30 MW31 Oct 2034ScopingMybster 4 132/33 kV GSP Substation
Nairn BESSBattery storage29.36 MW31 Oct 2026ScopingNairn 132/33kV Grid Supply Point Substation

Counts of what the registers printed. No score and no rank.

Supported by National Energy SO Open Data
Contains data from Scottish and Southern Electricity Networks, licensed under CC BY 4.0.
Supported by NGED Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.